Since its opening at Ang Mo Kio in 1999, the LFS has progressively
reached its maximal capacity and it has become indispensable to
find a solution to welcome the new students:
-Move temporarily for 2 years from September 2008 the Kindergarten
and a part of the Primary (CP/CE1) to the former Serangoon Garden
South School close to the LFS.
-Build a new block in place of the Kindergarten in order to get
26 additional classrooms.
-Transformation of the bus bay.
-Increase the canteen capacity.
-In option: expansion of the auditorium
-In option: a new sports room
You will find below some information and pictures regarding the
extension project.
|
 |
| |
|
LFS serangoon site :
- Tenancy Agreement signed on 01/01/2008 for 3 years.
- Renovation works from January to June 2008.
- Access works in July and August 2008.
- Moving in July 2008.
- Kindergarten: 19 classrooms, 1 library and 2 rest areas.
- Primary CP/CE1: 16 classrooms and 1 library.
- Facilities: 1 gymnasium partitioned in 2 parts, 1 canteen, offices,
1 swimming pool, 1 infirmary and playgrounds.
- Opening in September 2008
|
|
|
|
|
Kindergarten building
|
Kindergarten playgrounds
|
|
|
|
|
|
central field
|
Primary school building
|
Primary school playground
|
|
|
|
|
|
|
swimming pool
|
|
click on the thumbnails
to have a bigger picture !
|
LFS Ang Mo kio site :
- Demolition of the Kindergarten block (called block A) from July 2008.
- Construction works from July 2008 to August 2010.
- New five-storey block in order to get 26 additional classrooms plus
facilities.
- Bridge connecting the new block to the current primary block.
- Welcome 2000 students from September 2010.
|
|
|
|
|